Beyond Technical Execution: Rethinking Renewable Development for an Era of Stakeholder Risk
By Varun Gowda and Patrick Woods ·
In 2024, after two years of planning and preparation, the path appeared clear for Frasier Solar’s 120-megawatt project in Knox County, Ohio. The project, spanning portions of Miller Township, Clinton Township, and the City of Mount Vernon, was expected to generate more than $40 million for local governments and schools over its 40-year life. Early township meetings in 2022 and 2023 drew little public attention, and those who did attend were generally supportive. Frasier and its developer, Open Road Renewables, were prepared to move forward.
It almost didn’t happen. Seemingly overnight, “everything exploded,” as Clinton Township Trustee Jay Maners later recalled.
Opposition rapidly organized. Public meetings became contentious, and misinformation spread through the community. None of the project’s engineering had changed, nor had the solar resource or its financing.
What changed was the stakeholder landscape. Community sentiment shifted, and new voices entered the conversation. Local politics became increasingly volatile. Frasier and Open Road were caught off guard — so much so that they nearly lost the job.
None of the project’s engineering had changed, nor had the solar resource or its financing. What changed was the stakeholder landscape.
This story is far from unique. Across the United States, renewable developers have become remarkably sophisticated at modeling land suitability, engineering constraints, interconnection costs, and project economics. Public support for renewable energy also remains broadly favorable. Yet projects continue to stall, sometimes after years of planning and millions of dollars invested.
What’s behind the disconnect? If developers have gotten so adept at technical planning and execution, what are they missing?
The answer lies in a fundamental shift in the nature of development work. The industry’s biggest execution challenges are no longer engineering problems to be solved once, but adaptive stakeholder challenges that evolve continuously over the life of a project. And most developers still manage them with operating models designed for a far more predictable world.
Because of this, developers cannot look solely to better engineering models or more project data to keep their projects on track. The real competitive advantage will come from building organizations that can understand, coordinate, and adapt to stakeholder dynamics with the same rigor they’ve already applied to technical execution.
The Renewable Development Paradox
On the surface, today’s renewable development landscape appears healthy. Public support for renewable energy is strong by historical standards. Development pipelines are robust, and the industry’s technical capabilities continue to advance.
Pew Research Center’s latest national survey illustrates the first part of that picture.
Majority of Americans say the government should encourage the production of wind and solar power
% who say the federal government should __ each of the following activities
Pew Research Center
Source: Survey of U.S. adults conducted March 16–22, 2026. “Americans’ Shifting Views on Energy Issues”
If public sentiment were the primary determinant for successful renewable development, these numbers would suggest an industry positioned for continued growth. Yet, developers are reporting something very different.
Research from Lawrence Berkeley National Laboratory found that approximately one-third of large wind and solar siting applications submitted between 2019 and 2023 were ultimately canceled, while roughly half experienced delays of at least six months. Developers estimated average sunk costs exceeding $2 million for canceled solar projects and $7.5 million for dropped wind projects, with delays adding roughly $200,000 per megawatt in extra costs.
The trend is bigger than individual projects. According to Columbia University’s Sabin Center, 498 renewable energy facilities were facing organized opposition as of mid-2025 — a 32% increase from the previous year. More broadly, 459 jurisdictions across 44 states have enacted severe restrictions on renewable energy development.
Even federal permitting, which affects a relatively small share of projects, demonstrates the broader challenge. Projects requiring intensive federal review frequently face timelines stretching five to seven years or longer.6 In a recent Crux survey, 94% of developers with delayed or abandoned projects cited federal permitting as a contributing factor, 80% said they now avoid sites likely to trigger federal review, and every respondent reported higher-than-expected project costs.
While none of these statistics is surprising on its own, the collective effect reveals a striking contradiction.
Few aspects of renewable development have seen more innovation over the past two decades than technical project planning. Site selection has become increasingly data-driven. Interconnection modeling has grown more sophisticated. Engineering workflows have matured. Developers can evaluate project economics and technical feasibility with unprecedented precision. On top of all that, public support remains broadly favorable.
Yet, in spite of these advancements, successfully moving projects from concept to construction appears to be getting harder rather than easier.
The expectation
- Public support favorable by historical standards
- Robust development pipelines
- More sophisticated siting, interconnection, engineering, and financial modeling than ever
The reality
- avg. sunk cost, canceled solar
- $2M+
- avg. sunk cost, dropped wind
- $7.5M
- facilities facing organized opposition (+32%)
- 498
- jurisdictions in 44 states with severe restrictions
- 459
Rather than asking whether renewable projects are technically viable, we should be asking why so many technically viable projects struggle to reach execution.
Development Projects Now Hinge on Relationships
Viewed through a purely technical lens, projects like Frasier Solar are difficult to explain. But, underneath the mystery are some clear signs of what’s holding many projects back.
The simple truth is that technical readiness is only one part of the equation. Renewable projects advance through a web of relationships among local governments, landowners, agencies, community organizations, and residents. County commissioners, township trustees, planning boards, regulatory agencies, landowners, neighboring residents, community organizations, and local business leaders all play different roles in charting a project’s course. Some make formal decisions. Others shape public opinion. Still others influence the people who ultimately cast the deciding votes.
- Make formal decisions
- Shape public opinion
- Influence those who decide
The stakeholder web. Influence rarely flows straight to the project. It moves through neighbors, organizations, and trusted local voices before it reaches the people who vote.
As projects have grown larger, more visible, and more interconnected with local economic and political priorities, these stakeholder dynamics have moved from the margins of development to its center. Recognizing how influence moves through that landscape has become as important as understanding the physical characteristics of the project site.
The Expanded Role of the Developer
Few people have witnessed that evolution more directly than Mike Volpe, chief development officer and co-founder of Open Road Renewables — the developer for the Frasier Solar project. Reflecting on how the role of a renewable developer has changed, he observed:
“I’m an engineer. I’m an MBA. I have become a political strategist mapping out nonlinear decisions where the human element the cultural compatibility, cultural resonance, and cultural identity is what’s making these infrastructure decisions.”
Open Road Renewables
“I’m an engineer. I’m an MBA. I have become a political strategist mapping out nonlinear decisions where the human element — the cultural compatibility, cultural resonance, and cultural identity — is what’s making these infrastructure decisions.”
In other words, technical expertise is no longer sufficient on its own. Developers must also understand how to build trust, where influence resides, how local concerns spread through a community, and which relationships are most likely to shape the outcome of a project.
Volpe and his team make this especially tangible through what they call “Dirty Boots” campaigns. Early in the development process, Open Road identifies respected local farmers and landowners — the “Dirty Boots” — whose opinions carry weight well beyond their own property lines. As he explains, “The Dirty Boots actually set the cultural identity in these rural communities.”
Their influence isn’t formal. They don’t necessarily hold elected office or serve on permitting boards. But they shape how neighbors interpret new information and how a project is perceived within the broader community. Identifying and engaging with those key players is now a foundational step in the development process.
Stakeholder Risk Is Execution Risk
Importantly, this isn’t just a question of community outreach. A respected local voice can legitimize a project — or lend credibility to opposition. A shift in community sentiment can alter the political environment surrounding permitting decisions. A new coalition can emerge in a matter of weeks, as in the case of Frasier Solar, changing the assumptions under which a project team has been operating for months or even years.
Unlike many technical challenges, these dynamics don’t always present opportunities for redesign or optimization. Once relationships deteriorate or community trust erodes, developers may have few practical options beyond absorbing delays, accepting new conditions, or abandoning a project altogether.
Stakeholder dynamics have become such a consequential source of execution risk. Engineering challenges can often be solved through redesign and financial assumptions can be updated. But when the human dynamics surrounding a project grow volatile, the consequences are often far less forgiving.
Yesterday’s Operating Model Meets Today’s Development Reality
None of this is to say that developers don’t understand stakeholder dynamics. In fact, most experienced teams understand them quite well. The challenge is that many organizations still manage stakeholder work using operating models built for a more procedural development process.
Traditionally, that made sense. Many aspects of renewable development could be broken into discrete workstreams with clearly defined owners, deliverables, and handoffs:
- Engineering advanced through established design phases.
- Environmental studies followed predictable workflows.
- Permitting often centered on preparing documentation, securing approvals, and moving the project to its next stage.
Stakeholder work doesn’t generally move that way. New commitments create downstream obligations. Elections change local priorities, and community concerns evolve as projects mature. Information that seems peripheral one week can alter a project’s trajectory the next. Rather than progressing through a series of completed tasks, stakeholder work requires organizations to continually reassess, coordinate, and adapt as conditions change.
Coordination Lags Behind Complexity
As stakeholder work has grown more dynamic, many organizations have responded by adding new tools, new data sources, and new reporting processes. That produces an ecosystem of specialized systems designed to support individual teams and disciplines — a helpful setup only insofar as stakeholder work stays within the boundaries of a single team. As most developers know, that’s rarely the case.
“Some people will do their own custom instance of ArcGIS, which is meant to put all the data layers into one. But then those systems don’t talk to each other. Or, some teams are still using Excel, and then it’s getting stitched into reporting channels through Smartsheet.”
Developer & IPP with 25GW portfolio
A former senior vice president of development with 25GW portfolio puts his finger on an increasingly common experience. “Some people will do their own custom instance of ArcGIS, which is meant to put all the data layers into one,” he explains. “But then those systems don’t talk to each other. Or, some teams are still using Excel, and then it’s getting stitched into reporting channels through Smartsheet.”
None of these tools is inherently inadequate, but each one was designed to solve a particular problem for a particular team. Stakeholder work, however, cuts across every function in the organization. As information becomes fragmented across systems and ownership boundaries, it grows increasingly difficult for the organization to maintain a shared understanding of what is changing and what those changes require.
Institutional Knowledge Doesn’t Stay Institutional
Coordination challenges are only part of the problem. Just as consequential is what happens to the knowledge organizations accumulate throughout the development process. Every stakeholder conversation, community meeting, landowner discussion, and permitting negotiation produces information that can influence future decisions. Much of that knowledge never appears in a formal filing or engineering report. It exists in phone calls, meeting notes, consultant updates, email threads, and the experience of individual team members.
“You have countless conversations like this in this role, and capturing those is really important,” explains a senior solar development manager with 12+ GW portfolio. “Doing what you say you’re going to do as a developer is huge. But when you spend all day on the phone, and you don’t take notes, that’s a problem.”
“Doing what you say you’re going to do as a developer is huge. But when you spend all day on the phone, and you don’t take notes, that’s a problem.”
Developer and IPP with 12+ GW portfolio
As development progresses, those conversations become commitments — to landowners, elected officials, agency staff, and community members. If those commitments aren’t consistently documented, shared, and carried forward, organizations risk losing something far more important than information. They risk losing trust.
“All those commitments that we make during development to the landowner, to the community, in a permit condition, those need to continue past development,” the development manager adds.
In other words, capturing stakeholder information is only one small piece of the puzzle. When institutional knowledge remains trapped in individual conversations, scattered across systems, or leaves with the people who hold it, organizations lose the ability to adapt as a coordinated whole.
Adaptive Work Requires Adaptive Coordination
Given these realities, Mike Volpe describes today’s development process as a series of decision points rather than a fixed sequence of tasks. Throughout a project’s lifecycle, teams continually weigh whether to advance engineering work, commit additional capital, or defer major investments until key permitting decisions have been resolved. Those choices depend on the organization’s latest understanding of stakeholder conditions, permitting progress, and project risk.
Each new stakeholder conversation, community commitment, permitting milestone, or political development has the potential to change not only the work of a community engagement team, but also engineering priorities, permitting strategy, capital deployment, and project timelines. Information must not only be recorded but ultimately reach the people whose decisions depend on it — and do so while there’s still time to change course.
Traditional operating models weren’t designed for that kind of work. They excel at assigning ownership, tracking deliverables, and moving projects through established processes, but they struggle with letting new information continuously reshape decisions across multiple teams.
That’s the heart of today’s development challenge: organizations are increasingly trying to manage adaptive work with operating models designed for procedural work.
Toward a New Operating Model for Adaptive Work
If today’s development challenges stem from a mismatch between the work and how organizations are structured to manage it, then solving those challenges requires rethinking the operating model itself.
That doesn’t mean abandoning the technical rigor that has made renewable development increasingly sophisticated. Engineering, permitting, finance, and stakeholder engagement remain distinct disciplines, each with its own expertise and responsibilities. The opportunity lies in helping those disciplines operate as a coordinated system — one that can recognize change, understand its implications, and respond before subtle shifts become costly surprises.
Organizations built for adaptive work tend to share four capabilities, none of which exists in isolation. Each reinforces the others, creating an operating model that continuously translates changing stakeholder conditions into coordinated execution.
An operating model for adaptive work. Four capabilities that reinforce one another, anchored by a living stakeholder model.
Capability 1: Shared Situational Awareness
One common picture of what has changed, why it matters, and where to look next.
Adaptive work depends on a shared understanding of the project’s current reality. That sounds straightforward, but it’s surprisingly difficult when stakeholder information is constantly emerging from different conversations, disciplines, and external sources.
Viewed in isolation, a change in permitting assumptions from a county commission meeting or a landowner’s new concern about property values may seem minor. Taken together, however, they may fundamentally alter the course of a project.
Organizations built for adaptive work create mechanisms for those signals to converge into a common operating picture. Rather than leaving each team to interpret events through the lens of its own responsibilities, they establish a shared understanding of what has changed, why it matters, and where to direct attention next.
That shared situational awareness becomes the foundation for every capability that follows. Without it, teams may continue executing their own work effectively while the organization as a whole moves in the wrong direction.
Capability 2: Connected Decision-Making
Turning shared understanding into coordinated action without centralizing every call.
Shared situational awareness has limited value if it doesn’t influence decisions across the organization. Once teams have a common understanding of what’s changed, the next challenge is ensuring that understanding consistently informs decisions across the project.
Ultimately, that requires a way to consistently connect new stakeholder developments with the decisions they affect. Teams need to understand not only what has changed, but also which priorities, assumptions, and next steps should change with it.
Organizations built for adaptive work make that process intentional. Rather than relying on individuals to recognize implications and manually coordinate responses across teams, they establish clear pathways for turning new understanding into coordinated action. Decisions are still distributed across the organization, but they are guided by a shared understanding of the project’s current reality.
This doesn’t necessarily require centralized decision-making, which can slow projects as much as poorly informed decisions. Instead, it creates a more synchronized organization that can adapt quickly without depending on constant meetings, manual coordination, or individual heroics.
Capability 3: Deep Organizational Memory
Commitments and context that stay with the project, not with the people.
Adaptive work also depends on preserving what the organization learns along the way. As the development manager noted earlier, stakeholder conversations create commitments that often extend well beyond the development phase. Organizations built for adaptive work ensure those commitments — and the context behind them — remain attached to the project rather than the memory of the people who happened to be involved.
Agreements made during permitting remain visible through construction and operations. Community concerns raised early in development continue to provide context for later decisions. Even as projects change hands and teams evolve, the reasoning behind past choices remains accessible.
This creates continuity across both projects and people. Knowledge no longer depends on who happened to attend a meeting or which employee remembers a particular conversation. The organization develops a durable institutional memory that preserves context, reinforces accountability, and enables future decisions to build on what has already been learned.
Capability 4: Continuous Execution
Plans that keep pace with the stakeholder landscape, not the review calendar.
The first three capabilities ultimately exist to keep execution aligned with the project’s current reality. As stakeholder conditions change, organizations built for adaptive work don’t wait for formal stage gates or periodic project reviews to reassess their plans. They continuously evaluate whether priorities, assumptions, and next steps still reflect current conditions, allowing adjustments before small changes compound into delays, rework, or unnecessary risk.
The result is a development process that remains both disciplined and adaptable. Projects continue to move through established technical workflows, but those workflows continually respond to changes in the stakeholder landscape rather than becoming disconnected from it.
Combined, these four capabilities allow organizations to operate with a fundamentally different rhythm — not reacting to stakeholder developments after they disrupt a project, but continuously incorporating them into how projects are planned, coordinated, and executed.
From Principles to Practice
Understanding the key capabilities needed for adaptive work is foundational, but it naturally leads to the final critical question: How do organizations actually build those capabilities?
At the center of adaptive operations is a living stakeholder model. Unlike a traditional stakeholder database or CRM, a living stakeholder model isn’t simply a repository of contacts, notes, or meeting records. It serves as a continuously evolving representation of the project’s stakeholder landscape, capturing not only who the stakeholders are but also their relationships, commitments, influence, and priorities, as well as how those dynamics change over time.
Imagine a project where every significant stakeholder interaction immediately becomes part of the organization’s shared understanding of the project. New commitments remain attached to the project throughout its lifecycle. Changes in sentiment, influence, or permitting conditions become visible across teams. Rather than waiting for information to be manually reconciled through meetings, spreadsheets, and email threads, the organization continuously updates its understanding of the stakeholder landscape as the project evolves.
That is what a living stakeholder model makes possible. Built properly, supporting technology can enable each of the capabilities described:
- Shared situational awareness: Every significant stakeholder development contributes to a common operating picture rather than remaining isolated within individual teams. Stakeholder trackers, geographic views, sentiment mapping, and dynamic assessments of stakeholder alignment help maintain that shared understanding as conditions evolve.
- Connected decision-making: New stakeholder developments are evaluated in context and surfaced to the teams and workstreams they are most likely to affect, allowing coordinated decisions while meaningful options still exist. Activity feeds, intelligent notifications, and cross-functional workflows help ensure that changing stakeholder conditions influence execution rather than remaining isolated as updates or observations.
- Organizational memory: Every conversation, commitment, and stakeholder interaction becomes part of the project’s institutional knowledge rather than the memory of the individuals involved. Commitment tracking, CRM functionality, and project historians preserve not only what happened but also why decisions were made and how relationships progressed.
- Continuous execution: As stakeholder conditions evolve, project priorities and execution adapt accordingly. Rather than waiting for periodic reviews or manual coordination, development teams continuously align engineering, permitting, community engagement, and capital decisions with the project’s current stakeholder reality.
Enabling these capabilities requires technology designed to function as a coordination layer across the development organization — one that continuously connects stakeholder intelligence to the decisions and workflows it affects.
As new information enters the system, the goal isn’t simply to document it. The technology helps maintain a living picture of stakeholder relationships, preserve commitments made throughout development, surface emerging risks, identify downstream implications, and keep the right people informed as conditions change. Instead of forcing teams to manually reconcile spreadsheets, meeting notes, GIS layers, consultant reports, and email threads, the organization operates from a continuously updated understanding of the project’s stakeholder landscape.
Technology alone won’t solve the challenges described in this paper. But when combined with an operating model designed for adaptive work, it gives developers something they’ve rarely had before: the ability to translate changing stakeholder conditions into coordinated execution before those changes become project delays.
The Next Competitive Advantage
The renewable industry has spent the past few decades dramatically improving its ability to evaluate technical risk. Developers can model interconnection constraints, optimize engineering designs, analyze project economics, and assess site suitability with remarkable precision. Those capabilities have become essential to modern development, but they are no longer sufficient.
As projects become increasingly shaped by local relationships, evolving community dynamics, and interconnected stakeholder decisions, execution depends on more than technical excellence. It requires an organization to recognize change early, coordinate decisions across disciplines, preserve critical context, and continuously adapt as projects evolve.
The industry’s next competitive advantage will come from building organizations that can translate changing stakeholder conditions into coordinated execution.
That shift requires both an operating model and the supporting technology to treat stakeholder intelligence as a living part of project execution rather than a collection of notes, documents, and disconnected conversations.
That is the vision behind neuroGrid — the first orchestration engine for renewables — a tool designed to support the adaptive operating model that modern renewable development increasingly demands.
If your organization is exploring new ways to reduce stakeholder risk, improve coordination, and strengthen project execution, we’d welcome the opportunity to continue the conversation.