Aerial illustration of a large industrial campus under construction in rolling countryside

Electricity Demand Is Rising Again. The Bottleneck Is Execution

By Michael Holbrook ·

From where we stand now, it’s hard to believe that electricity demand growth ran almost flat for 15 years. Consumption increased at a snail’s pace from 2005 to 2020, growing at only 0.1% per year on average.

Bar chart titled “It’s not just AI”: share of the increase in global electricity demand by sector, 2024–30. Industry 29.8%, electric transport 12.9%, appliances 11.7%, space cooling 10.0%, data centers 8.2%, space and water heating 7.0%, other 20.4%.

Source: Nat Bullard, Decarbonization: Parameters, Dollars and Sense, Electrons Photons Molecules

But since 2020, demand growth has accelerated to roughly +1.7% annually, creeping back toward the dot-com high of 2% from 1990-2005. Given the timing, it’s tempting to assume this is all driven by AI. And data centres are clearly a major driver — some projections suggest their electricity consumption could double or even triple by 2028, reaching as much as 12% of U.S. load.

But is it really all because of AI? It may be the loudest contributor to this upswing, but it’s clearly not the only one. Nor is it necessarily the largest. Nat Bullard recently drew attention to the fact that global electricity demand growth this decade isn’t driven solely by data centers. Industrial electrification accounts for an even larger share, alongside trends like EV adoption, building electrification, and clean fuel production.

In other words, this isn’t a single demand shock. It’s multiple adoption curves arriving at once. And those curves are compounding, not replacing one another, while infrastructure execution still moves sequentially.

As I see it, that’s an important distinction for developers. When demand stacks unevenly and regionally — instead of rising gradually across the system — it changes the risk profile. And it raises the question of whether projects can be delivered on timelines that match where that load is actually showing up.

This isn’t a single demand shock. It’s multiple adoption curves arriving at once.

There Is a Deliverability Capacity Shortfall — And It’s Regional

NERC’s 2025 Long-Term Reliability Assessment identifies elevated or high resource adequacy risk in 13 of 23 assessment areas over the next five years. The map tells the story: certain regions face significant near-term stress as load forecasts rise faster than resource and transmission additions.

Map of North American reliability assessment areas shaded by resource adequacy risk over the next five years, with high-risk and elevated-risk regions labeled by the year risk begins.

Source: NERC 2025 Long-Term Reliability Assessment

But it’s important to read NERC’s conclusion carefully. The report does not identify a shortage of generation technology or investor interest as key reasons for the shortfall. In fact, solar, storage, and natural gas additions dominate planned additions over the next decade. At the same time, fossil retirements continue, and the resource mix is shifting toward more weather-dependent generation. The core risk NERC highlights is that projected resource and transmission growth — combined with retirements and rising demand — may not keep pace in several regions.

What does that mean? This is a structural throughput problem: how quickly planned megawatts can become operational megawatts in places where the demand curves are compounding.

Interconnection queues now stretch years, with attrition rates rising as projects stall or reprice. Transmission upgrades often require three to five years — sometimes longer — from approval to energization. In many regions, substations are already operating near capacity. Policy volatility can chill long-lead investment decisions. Even manufacturing capacity tightens when uncertainty delays firm commitments.

All of this changes the underwriting calculus for developers. It’s no longer enough to secure land, lock in equipment, and model commodity pricing. Interconnection timing becomes a first-order risk variable. Transmission alignment becomes a gating factor. “Planned capacity” is not the same as deliverable megawatts.

As demand stacks unevenly and regionally, the crucial differentiator is whether your project can be energized on the timeline your capital stack assumes.

The crucial differentiator is whether your project can be energized on the timeline your capital stack assumes.

Demand Is Accelerating in Real Time — Infrastructure Is Delivered in Planning Cycles

In the previous decade, infrastructure planning operated on relatively stable assumptions. Load growth was incremental, and interconnection queues moved predictably (if slowly). Transmission planning followed multi-year review cycles that suited gradual demand growth.

These timelines no longer line up. Large-load commitments can reshape a regional forecast in months. Electrification policies accelerate adoption. Industrial siting decisions cluster demand geographically. Meanwhile, transmission and substation upgrades still move through multi-year processes. And what we get is much more than a simple delay – it’s misalignment. Infrastructure timelines are still measured in years, while demand forecasts, capital commitments, and regulatory assumptions change in real time.

What we get is much more than a simple delay — it’s misalignment.

Shared network upgrade

Four projects in the cohort

ABC D

25% of the cost each

Project D withdraws

Three projects absorb its share

ABC

~33% of the cost each

One exit reprices everyone. Assumes equal shares. Actual allocations depend on study results and each market’s tariff rules.

If you’re developing projects today, you see that misalignment immediately in the mechanics.

A Generator Interconnection Agreement (GIA), for instance, defines binding milestones, upgrade obligations, and cost responsibilities tied to specific study assumptions. When load forecasts shift or cluster studies are rerun, upgrade allocations can change. In large markets, layered network upgrade costs are often shared across project cohorts. If one project drops out, the cost responsibility for others may be recalculated. If load growth accelerates in a pocket of the system, previously sufficient infrastructure can suddenly require reinforcement.

Again, the response challenge isn’t a lack of generation technology. It’s figuring out how to recalibrate a system under moving assumptions.

Even in regions aggressively adding renewables with storage — the fastest form of new generation to deploy — speed at the plant level doesn’t eliminate sequencing challenges down the line. Solar and storage still:

  • Require executed interconnection agreements
  • Depend on transmission capacity being in service
  • Need local approvals, stakeholder alignment, procurement coordination, transformer availability, and substation capacity

The turbines, panels, and batteries may be build-ready, but the grid connection is not always timeline-ready.

That is the compression developers are navigating. Infrastructure planning cycles were built for incremental growth, but overlapping demand drivers are arriving faster than those cycles can comfortably absorb.

A Structural But Solvable Shortfall

None of this is to suggest that the grid is incapable of meeting this surge in demand. In fact, the opposite is true.

The U.S. added more than 30 GW of new solar generating capacity in the first three quarters of 2025. Natural gas projects continue to move through planning queues in targeted regions. NERC’s report highlights 41,000 miles of planned transmission expansion. Demand flexibility — from large industrial loads to data center curtailment agreements — offers new tools for managing peak strain.

30+ GW

new solar capacity added in the first three quarters of 2025 (SEIA)

41,000 mi

of planned transmission expansion (NERC)

Flexible load

industrial and data center curtailment agreements to manage peaks

The tools exist. The question is whether they can be sequenced in time.

But all of these options matter only if they can be sequenced effectively.

For developers, that means prioritizing regions with realistic transmission headroom rather than chasing headline demand growth. It means underwriting substation capacity and upgrade exposure, not just forward power curves. It means modeling multiple energization pathways and considering phased buildouts or hybrid strategies.

But most of all, it means coordinating these decisions earlier — and more tightly — across interconnection, engineering, siting, landowner and stakeholder engagement, and capital planning. In a compressed environment, sequencing errors propagate quickly. A misaligned upgrade assumption, a delayed study milestone, or a stalled landowner agreement doesn’t simply push a schedule — it alters downstream commitments.

In a compressed environment, sequencing errors propagate quickly.

From Capacity to Delivery

The industry keeps asking whether we have enough generation. I think we’re asking the wrong question. The real issue is whether we can move planned capacity into service at the pace demand now requires.

The grid is capable, the technology is available, and the capital is there to generate power. The constraint is throughput — how quickly ideas, permits, capital, and steel convert into energized megawatts.

The constraint is throughput — how quickly ideas, permits, capital, and steel convert into energized megawatts.

The key takeaway for developers is that timing is now a central risk variable. And problems occur when timeline volatility surfaces inside project economics. That’s the topic for our next post in this series.

If your organization is exploring new ways to reduce stakeholder risk, improve coordination, and strengthen project execution, we’d welcome the opportunity to continue the conversation.